Overhead cranes, new or old installed, must be tested and certificated qualified, and get the acceptance inspection, before being put into work. Crane inspection and crane testing are necessary and important for crane commissioning and crane acceptance, which is indispensable procedure to check the overhead crane manufacturing and installation quality, and guarantee crane safety during operation.

Overhead crane commissiong
Besides crane commissioning and acceptance inspection, the regular overhead crane inspection and loading test are required each and every year. However, in the following, the crane test and crane inspection for overhead crane commission and acceptance will be put in length.
For a newly installed overhead crane or overhauled crane, before commissioning, we should organize experienced electrician, fitter, crane operators and relevant technical personnel to check the overhead crane comprehensively. The crane inspection main contents are as follows:
1) Cut off the power supply of the overhead crane before inspection. According to the crane drawings and technical requirements, check and ensure:
2) Check and make sure all rotating device is installed correctly and is able to rotate correctly and flexibly. Turn the wheel by hand and observe the moving of the output shaft and the revolving of the driven organization, making sure all are in stable rotation, with no block or stuck.
3) Overhead crane brake should be accurate and reliable. Two brakes should be consistent with each other, which are installed for the running mechanism of overhead crane.
4) All lubricating points should be lubricated with the required lubricating oil according to the rules and oil amount on reducer shall be within the prescribed scope.
5) Electrical equipment inspection
After inspection and preparation, the overhead crane operation test can proceed. The running test of overhead crane can be divided into the following three steps: no-load test, static load test, and movement test.
10 ton electric hoist testing
Overhead crane no-load test are mainly divided into the three parts, the crane trolley travelling test, overhead crane travel test, and no-load hook test.